New Contract for Safaniya Offshore
Posted: 22 August 2005
Send this article
Saudi Aramco Pr oject Management recently signed a contract with National Petroleum Construction Company (NPCC) Abu Dhabi for work on the north Safaniya offshore oil field.
The project involves the installation of 42 Electric Submersible Pumps (ESP) on seven existing platforms.
Additionally, mezzanine decks will be added to the existing platforms to accommodate the ESP service equipment.
Subsea power cables will be installed along with new flanklines and a 42", 50km trunkline from a new tie-platform to onshore Safaniya GOSP-1.
Posted by Editor Pipeline Magazine
Replication or redistribution in whole or in part is expressly prohibited without the prior written consent of Reflex Publishing ME FZ LLC.
Send press release to info@pipelinedubai.com |