Hurricane Katrina Evacuation and Production Shut-in Statistics Reportas of Thursday, September 15, 2005
Posted: 19 September 2005
Send this article
Print this article
This survey reflects 54 companies’ reports as of 11:30 a.m. Central Daily Time.
Districts |
Lake Jackson |
Lake Charles |
Lafayette |
Houma |
New Orleans |
Total |
Platforms Evacuated |
0 |
0 |
0 |
2 |
82 |
84 |
Rigs Evacuated |
0 |
0 |
0 |
0 |
2 |
2 |
|
|
|
|
|
|
|
Oil, BOPD Shut-in |
0 |
620 |
1,122 |
61,787 |
778,562 |
842,091 |
Gas, MMCF/D Shut-In |
0 |
22.00 |
3.00 |
447.79 |
2,938.05 |
3,410.84 |
These evacuations are equivalent to 10.26% of 819 manned platforms and 1.49% of 134 rigs currently operating in the Gulf of Mexico (GOM).
Today’s shut-in oil production is 842,091 BOPD. This shut-in oil production is equivalent to 56.14% of the daily oil production in the GOM, which is currently approximately 1.5 million BOPD. Approximately 35% of shut-in oil is as a result of problems with onshore infrastructure.
Today’s shut-in gas production is 3.411 BCFPD. This shut-in gas production is equivalent to 34.11% of the daily gas production in the GOM, which is currently approximately 10 BCFPD.
The cumulative shut-in oil production for the period 8/26/05-9/15/05 is 21,375,721 bbls, which is equivalent to 3.904 % of the yearly production of oil in the GOM (approximately 547.5 million barrels).
The cumulative shut-in gas production 8/26/05-9/15/05 is 102.405 BCF, which is equivalent to 2.806% of the yearly production of gas in the GOM (approximately 3.65 TCF).
These cumulative numbers reflect updated production numbers from all previous reports. The reports only represent input received by 11:30 a.m. CDT . If a company does not report by 11:30 a.m. it is not included in the special information release, but it is included in the cumulative shut-in production. This may result in an apparent increase in the cumulative report amount.
Shut-ins for oil and gas production are standard procedures conducted by industry for safety reasons. Once facilities have been inspected and all standard checks have been completed the production for these facilities will be brought back on line.
The MMS will continue to update the shut-in statistics at 1:00 PM CDT each day until these statistics are no longer significant
Posted by Editor Pipeline Magazine
Replication or redistribution in whole or in part is expressly prohibited without the prior written consent of Reflex Publishing ME FZ LLC.